Floor slab is concreted to perimeter of hydro pool and Water Play Room.
Cutting, placing and fixing of sole plates are almost complete.
Erection of perimeter scaffold is continuing.
Timber frame erection is continuing, fitting of floor cassettes and first floor walls started.
Block work to retaining wall has started.
So what's next?
Continue scaffold erection, fixing of sole plates, timber frame erection.
The steps and ramp being constructed within the hydrotherapy pool. |
The retaining wall being constructed |
View from the north |
First floor walls being erected |