Activity/Observations
Floor slab preparation, including placing of steel reinforcement, is continuing to perimeter of hydrotherapy pool and Water Play Room. Walls to Water Play Room have been concreted.
Cutting, placing and fixing of sole plates are continuing.
Erection of perimeter scaffold is continuing.
Base coat and binder layers of tarmac are laid to car park and access road areas.
High spots to concrete floor slab have been addressed.
Timber frame erection has started this week.
So what's next?
Continue floor slab / cantilevered floor around hydro pool, scaffold erection, fixing of sole plates, timber frame erection.
The reinforced sides of the water play area plant room showing the many pipe connections required |
The first timber frame panels are erected nearest the campus square. |
Soleplates and timber frame erection |