Tuesday 14 January 2014

Wyre Forest School - Contract Week 27



Forming the base of the hydrotherapy pool plant room
Excavating the base of the landscape retaining wall


View looking down on the ground floor walls (food tech and service areas)

Looking down on the sensory and soft play room areas
Building works this last week have included...

 Floor slab preparation, including placing of steel reinforcement, is continuing to perimeter of hydrotherapy pool and Water Play Room.
 Cutting, placing and fixing of sole plates are almost complete.
 Erection of perimeter scaffold is as required.
 Timber frame erection is continuing (first phase).
 Access road to Science Block has now been diverted to allow building of a retaining wall by the play area.
 Excavation for retaining wall is in progress.

So what's next?
 Continue floor slab / cantilevered floor around hydro pool, scaffold erection, fixing of sole plates, timber frame erection.