Monday 27 January 2014

Weekly Boarding - Contract Week 29

Progress this week:

Activity/Observations
 Roof tiling
 Roof Velux rooflights installations
 Acoustic insulation to internal partition walls + insulating quilt to outer walls
 Fermacell fire lining and plaster boarding continues to first floor
 Plaster board linings again mainly to first floor
 Electrical 1st fix, containment, baskets, etc
 Sprinkler 1st Fix
 Mechanical 1st fix + air ducting
 Floor paint applied to Boiler room
 External door and window installations, complete with exception of construction routes
 Warmcell insulation installations now complete
 Powder coated aluminium profiles above external openings/trim to cladding weather boarding
 Kerb racing to rear - dwarf retaining wall to rear

Factory coated timber board cladding being installed.


Mineral wool insulation installed to walls

The concrete base for the sprinkler tank