Monday 20 January 2014

Wyre Forest School - Week 28

A large lorry arrives to deliver more wall and floor panels


Geeting ready to cast the floor of the pool changing rooms


The floor being placed over the Food Technology Room


Erecting walls around the soft play room
 Progress on site this week:

Activity/Observations

 Floor slab preparation, including placing of steel reinforcement, is continuing to perimeter of hydrotherapy pool and Water Play Room.
 Cutting, placing and fixing of soleplates for the timber framed walls is almost complete.
 Erection of perimeter scaffold is continuing as required.
 Timber frame erection (Phase 1) is continuing, fitting of floor cassettes started this week.
 Excavation and concreting of foundation for retaining wall is complete.



So what's next?
 Continue floor slab / cantilevered floor around hydro pool, scaffold erection, fixing of sole plates, timber frame erection.