Activity/Observations
Roof tiling, later stages + proprietary flashing to Velux rooflights
Ongoing acoustic insulation to internal partition walls + insulating quilt to outer walls
Fermacell fire lining and plaster boarding continues to 1st and 2nd floors
Electrical 1st fix, containment, baskets, etc
Sprinkler 1st Fix
Mechanical 1st fix + air ducting
Cedar cladding, weather boarding + support framing
Kerb racing to rear - dwarf retaining wall to rear
Sprinkler tank fabrication
The major service trench connecting the builings on the site. The sprinkler supply pipe is laid first. |
Cellweb base laid for parking spaces - this protects the roots where parking is close to existing trees. |
Services being installed in one of the dining areas |
The sprinkler tank will be concealed by fencing and hedging |