Friday 31 January 2014

Weekly Boarding - Contract Week 30

Progress this week...

Activity/Observations
 Roof tiling, later stages + proprietary flashing to Velux rooflights
 Ongoing acoustic insulation to internal partition walls + insulating quilt to outer walls
 Fermacell fire lining and plaster boarding continues to 1st and 2nd floors
 Electrical 1st fix, containment, baskets, etc
 Sprinkler 1st Fix
 Mechanical 1st fix + air ducting
 Cedar cladding, weather boarding + support framing
 Kerb racing to rear - dwarf retaining wall to rear
 Sprinkler tank fabrication



The major service trench connecting the builings on the site. The sprinkler supply pipe is laid first.

Cellweb base laid for parking spaces - this protects the roots where parking is close to existing trees.

Services being installed in one of the dining areas

The sprinkler tank will be concealed by fencing and hedging