Thursday 2 January 2014

Week 24 - Weekly Boarding Unit (w/e 22 Dec 2013)

Progress this week:

Complete timber frame - continue roof counter battens (70mm x 75mm) Install Tyvek sarking – Fit cedar fascia/barge – Single ply to flat roof - roof tiles installation/loading out – lightning conduction
 Internal partition walls and floor zone 1st floor (to soffit) acoustic insulation + netting - commence floating/acoustic floor to 1st floor circulation areas
 Commence double layer fire line plaster boarding GF ceilings
 Electrical first fix, containment
 Sprinkler 1st Fix
 1st fix plumber SVP's
 External door and window installations + airtightness taping, etc
 Warmcell recycled insulation installations, walls completed, roof warmcell to follow
 Air tight membrane + taping now advanced
 Kerb lines to parking and approach, include line of swale + gas trench to meter housing
Roof tiles being set out ready for laying

Lightning conductor tapes being laid under the roof tiles

Pipework supports and pipework being installed above corridor ceilings

1 comment:

  1. Thank you for sharing such great information. It has help me in finding out more detail about solid wood flooring sale

    ReplyDelete