Complete timber frame - continue roof counter battens (70mm x 75mm) Install Tyvek sarking – Fit cedar fascia/barge – Single ply to flat roof - roof tiles installation/loading out – lightning conduction
Internal partition walls and floor zone 1st floor (to soffit) acoustic insulation + netting - commence floating/acoustic floor to 1st floor circulation areas
Commence double layer fire line plaster boarding GF ceilings
Electrical first fix, containment
Sprinkler 1st Fix
1st fix plumber SVP's
External door and window installations + airtightness taping, etc
Warmcell recycled insulation installations, walls completed, roof warmcell to follow
Air tight membrane + taping now advanced
Kerb lines to parking and approach, include line of swale + gas trench to meter housing
Roof tiles being set out ready for laying |
Lightning conductor tapes being laid under the roof tiles |
Pipework supports and pipework being installed above corridor ceilings |