Progress on the Special School this week in words and photographs:
Activity/Observations

 Cutting, placing and fixing of timber soleplates for walls are almost complete.
 Erection of perimeter scaffold is continuing.
 Timber frame erection is continuing, fitting of floor cassettes and first floor walls.
 Block work to retaining wall is continuing.
 Block walls and screeds to hydro pool is in progress.


So what's next?
 Continue scaffold erection, fixing of sole plates, timber frame erection, works to hydrotherapy pool.
The retaining wall is made of reinforced blockwork and will be faced with buff brick

The first floor walls being put up around the assembly hall, kitchen and dining areas

The steps and ramp being formed in the hydrotherapy pool


View of the school on the secondary school side