Corridor showing heating and water pipework installation above ceiling level |
View of the outside |
Activity/Observations
Roof tiling
Internal partition walls- acoustic insulation
Floating/acoustic floor to 1st floor rooms, also shower areas
Fermacell fire lining and plaster boarding mainly to first floor
Electrical 1st fix, containment, baskets, etc
Sprinkler 1st Fix
Mechanical 1st fix + air ducting
External door and window installations, complete with exception of construction routes
Warmcell recycled insulation installations to roof
Powder coated aluminium profiles above external openings
Air tight membrane + taping all completed
Kerb racing to rear + install gas main jointing + concrete floor slab poured to pump house/sprinkler tank area
Comments
INitial Air tightness test result @ 1.8
Sky lights to be fitted in-conjunction with roof tiling
Areas of fascia to be completed
Programme*
So what's next?
Outer cladding/internal finishing