Friday 17 January 2014

Weekly Boarding Unit - Contract Week 28

Corridor showing heating and water pipework installation above ceiling level

View of the outside
Progress this week...

Activity/Observations
 Roof tiling
 Internal partition walls- acoustic insulation
 Floating/acoustic floor to 1st floor rooms, also shower areas
 Fermacell fire lining and plaster boarding mainly to first floor
 Electrical 1st fix, containment, baskets, etc
 Sprinkler 1st Fix
 Mechanical 1st fix + air ducting
 External door and window installations, complete with exception of construction routes
 Warmcell recycled insulation installations to roof
 Powder coated aluminium profiles above external openings
 Air tight membrane + taping all completed
 Kerb racing to rear + install gas main jointing + concrete floor slab poured to pump house/sprinkler tank area
Comments
 INitial Air tightness test result @ 1.8
 Sky lights to be fitted in-conjunction with roof tiling
 Areas of fascia to be completed
Programme*

So what's next?
 Outer cladding/internal finishing