Monday 20 October 2014

Early Years Hub - Week 22

Activity/Observations Roof insulation and single ply to completion
 Window/door/curtain walling installations advanced
 Internal MF partitions + boarding
 Electrical containment + 1st fix
 Mechanical 1st and 2nd fix
 Air tightness membrane + tape, include lining insulation to completion
 External boarding cross battening ahead of cladding
 Levels reduced to west of building/campus square


Progress on the exterior facing Campus Square

Progress on the internal partitions

Pipework and equipment being installed in the plant room


Battens to the exterior being prepared to receive the cladding


Wyre Forest School - Week 67

Stair 2 being installed

The hydrotherapy pool being tiled with mosaic

The pool change area

The Sports Hall being prepared for painting

Floor finish being laid in teh Food Tech room

Catering Kitchen extract canopy

Main Foyer seen from the first floor
Activity/Observation
 M & E works are continuing.
 Internal boarding to walls and ceilings are continuing.
 Fitting of vertical slabs to the perimeter of the floor slab is to be completed.
 Single ply roof covering is progressing, flashings to complete.
 Fitting of cedar fascia's, barge boards and window cheeks are almost complete.
 Decorations are in progress.
 M.F. bulkheads, ceilings and suspended ceiling grids being erected.
 Wall tiling is in progress, including tiling to hydro pool.
 S.V.P.s and sink waste pipes being fitted and testing started.
 Plumbing panels are continuing.
 Works within Atrium is in progress.
 Gutter fixing is in progress.
 Internal staircases in place, one to complete.
 2nd fix Carpentry is progressing.
 Spine to Kitchen equipment is in place.
 Storm water drainage connections from down pipe positions continuing, foul manhole 8 is being constructed.
 Decking to enclosed external terraced areas is progressing.

So what's next?
 Continue scaffold dismantle, vertical slabs to floor slab, roof covering flashings, internal wall boarding, decorations and acoustic floor, 2nd fix Carpentry, M & E works, wall tiling, ceilings, soil and vent pipes.


Thursday 2 October 2014

Work starts on the Vocational Hub

Work has begun on the Vocational Hub, formerly E Block of Baxter College. The classrooms are being converted mainly for use by Wyre Forest School for vocational subjects, particularly for 6th formers, to study Food Technology/ Catering, Crafts, Art and DT. There will also be a cafe area with a servery accessed from Campus Square. Once Jack and Jill Nusery have moved to their new home in the Early Years Hub in February, a second phase of works in this block will convert their room to a Workshop where basic vehicle maintenance and other skills can be taught.



The new opening between the Art and DT rooms


New drainage being laid to serve the Food Tech room

Ceiling battens have been fixed for a new plasterboard ceiling

New kerbs for the paths from Campus Square into the Vocational Hub

Propping the roof whilst a steel beam  is inserted to enlarge the DT room