Monday 26 January 2015

Early Years Hub - Week 36


Activity/Observations 

 Carpets + protection

 Floor vinyl, now advanced and protected


 Electrical 2nd fix

  Mechanical 2nd fix, water heaters, etc.

  Plumber 2nd fix 

 Decorations

  Ceiling grids + lighting now advanced 

 Carpentry 2nd fix, 

 IPS, vanity units and proprietary cubicle partitions

 Canopy assembly




Wyre Forest School week 81

Progress this week:


Activity/Observation

 M & E 2nd fix/ finishing items are continuing.

 Single ply roof covering flashings to complete.

 Fitting of cedar fascias, barge boards and window cheeks are complete.

 Decorations are continuing.

 Wall and floor tiling to hydro pool is almost complete.

 Sanitary items being fitted.

 Plumbing panels are fitted, basin and hinged rail fixings to address.


 Gutter fixing is to complete.

Carpentry finishing items are in progress.


 Face brickwork to retaining walls are almost complete.

 Laying of vinyl floor covering and carpets are continuing.

 Furniture fitting is to complete.

 General external works continuing.


 Erection of canopies and glazing well advanced.


 Data installation progressing


The pavilion canopies (previously at Bewdley Road) have been installed at the new school.

The front canopy has been installed

Progress on the Primary outdoor areas

The assembly hall as seen from the dining area

Linoleum being laid around the atrium, level 1


Sixth form kitchenette

Key Stage 4 classroom

Friday 16 January 2015

Early Years Hub - Week 34



Activity/Observations

  • Floor vinyl, now advanced and protected
  • Install kitchenette units + fixed furniture
  •  Electrical 2nd fix
  • Mechanical 2nd fix, water heaters, etc.
  •  Plumber 2nd fix
  •  Decorations
  • Ceiling grids + lighting
  •  Carpentry 2nd fix,
  •  Plumbing systems, vanity units and proprietary cubicle partitions
  •  Data cabling
  • Mono blocks, campus square complete
  •  Canopy assembly imminent

The main entrance


Play areas being formed

Ramp up to the Wyre Forest School

Nursery areas and storage wall

Basins being fitted in toilet areas

Wyre Forest School -Week 80 (0verall contract week 94)

Progress this week:

  •  Mechanical & Electrical  2nd fix/ finishing items are continuing.
  •  Single ply roof covering flashings to complete.
  •  Fitting of cedar fascias, barge boards and window cheeks are complete, remedial works to do.
  •  Decorations are continuing.
  •  Tiles to ceilings almost complete.
  •  Wall and floor tiling to hydro pool is continuing.
  •  Sanitary items being fitted.
  •  Plumbing panels are fitted, basin and hinged rail fixings to be completed.
  •  Gutter fixing is to complete.
  •  Carpentry finishing items are in progress.
  •  Face brickwork to retaining walls are almost complete.
  •  Laying of vinyl floor covering and carpets are in progress.
  •  Furniture fitting is to complete.
  •  General external works continuing.
  •  Erection of canopies and glazing started.
  •  Data installation progressing.
  •  Site offices have been vacated this week, services disconnected and removal from site expected Friday of this week.
The covered canopy around the main entrance is being erected

The base for the Key stage 1/2 games court

Work progressing on the Primary outdoor areas

Floor laying in the Foyer

KS3 Classroom, carpets laid and protection laid over

The movable partition between the hall and dining areas is installed

First Floor landing by the atrium




Tuesday 13 January 2015

Vocational Hub- Latest Photos

The Design Technology Room
The art room
The Cafe

Food Tech/ Catering


Friday 9 January 2015

Habberley Learning Campus– Wyre Forest Special School Week 79

Levelling the area which will be the games courts (Key stage 1/2)

Landscaped play areas by the Primary classrooms

Secondary outdoor social areas and games court

Progress on the Foyer

The first carpets are laid in classrooms

The fitting out of the catering kitchen is well advanced

Key Stage 3 corridor

Stair and lift up to the hall and dining rooms
Progress this week:

Activity/Observation
 M & E 2nd fix/ finishing items are continuing.
 Acoustic separating floor system repairs and replacing of areas to complete.
 Single ply roof covering flashings to complete.
 Fitting of cedar fascias, barge boards and window cheeks are complete, remedial works to do.
 Decorations are continuing.
 Tiles to ceilings almost complete.
 Wall and floor tiling to hydro pool is continuing.
 Sanitary items being fitted.
 Plumbing panels are fitted
 Gutter fixing is to complete.
 2nd fix Carpentry is continuing.
 Face brickwork to retaining walls are almost complete.
 Laying of vinyl floor covering and carpets are in progress.
 Furniture fitting is to complete.
 General external works continuing.