Monday 13 January 2014

Weekly Boarding Unit - Contract Week 27


Weekly Boarding Unit - roof tiling continues

Rain channel in the garden made from paving setts


View of walls and roof : sealing and taping of all joints for airtightness

Internal wall showing the acoustic battening and resilient bars
Progress this week...

Activity/Observations
- Roof battening and tiling continuing
- Lightning conductors being installed
- Internal partition walls, acoustic insulation
- Floating/acoustic floor to 1st floor rooms, also shower areas
- Fire lining and plaster boarding mainly to first floor
- Electrical 1st fix, containment
- Sprinklers 1st Fix
- Mechanical 1st fix
- External door and window installations + airtightness taping, etc
- Warmcell recycled cellulose insulation installations, walls completed, roof warmcell to follow
- Air tight membrane + taping now advanced + air test to take place to check airtightness
- Kerb edging to parking and approach, include line of swale + install gas main housing to building