Activity/Observations
Fitting of air tightness tapes are complete.
Scaffold erection is continuing as required, internal and external.
Fitting of insulation, sound block plaster board and taping is complete to ground floor ceiling areas.
Fermacell boarding to ground floor classrooms are complete and atrium area has started.
Acoustic insulation to internal walls is advanced.
Acoustic ceiling to atrium is complete.
Sprinkler pipe work is complete.
Mechanical 1st fix continuing and 2nd fix has started.
Electrical 1st fix containment is continuing.
Single ply roofing to upper roof area is fitted, perimeter to do.
Acoustic flooring is continuing to first floor classroom areas.
Warm cell insulation to external walls has started.
So what's next?
Complete sarket board, scaffold erection, continue boarding ceilings, continue ducting, and mechanical pipe work, 1st fix electrics, fermacell boarding to internal walls, single ply roof coverings, warmcell insulation to external walls, acoustic flooring.
Warmcell recycled newspaper insulation ready to be pumped into the walls |
Water pipework systems being installed |
Typical laboratory with drainage systems being installed above ceilings for the lab above. |
No comments:
Post a Comment