Monday 24 March 2014

Weekly Boarding Unit - Week 37

Progress this week (week ending 23 March 2014):

Activity/Observations
 Roofing complete, high level work to weatherboard soffits
 Fermacell fire lining and plaster boarding continues to 1st and 2nd floors, includes taping/jointing.
 Boarding, ceiling panels now advanced – complete on 1st floor
 Continue electrical 1st fix – wiring to 1st floor complete
 Internal carpentry 2nd fix, doors (includes sliding doors + stud) and linings, stairs, kitchen units, cupboards, etc.
 Mechanical 1st fix /plumbing + air ducting + lagging
 Floor vinyl to Kitchen
 Commence decorations
 CIS installations - data cabling
 Rendering - knauf Marmorit system
 Coated aluminium gutters and downpipes
 Scaffold drop
 Ground works currently on hold awaiting areas to become available

The timber stairs are inserted

Rendered areas with shadow joints


Building approach from Moule Close

As seen from the garden