Wyre Forest School - Contract Week 35

Progress for the week ending 9 March 2014:

Activity/Observations

 Timber frame erection is continuing to areas 1 and 2.
 Service trench being excavated with laying of water main and ducts continuing.
 Distribution of windows into rooms ready for fitting has started.
 Fitting of bitroc sheathing board has started to external walls.


Programme*
 Battening of walls, window fitting to start during next week.
So what's next?
 Continue scaffold erection, timber frame erection, service trenches and ducts, fitting of bitroc,window fitting and battening.