Friday 14 March 2014

Weekly Boarding - Week 36

Progress up to 14 March 2014:



Activity/Observations
 Roofing complete, high level work to weatherboard soffits
 Fermacell fire lining and plaster boarding continues to 1st and 2nd floors, includes taping/jointing.
 Commence suspended perforated/ acoustic ceiling panels on acoustic resient-bar ceiling support grids, 1st floor corridor
 Continue electrical 1st fix
 Pipe lagging to voids and above ceilings
 Internal carpentry 2nd fix, doors and linings
 Mechanical 1st fix /plumbing + air ducting + boilers installed – IPS installations (proprietary WC cubicles now on site)
 CIS installations
 Cedar cladding, weather boarding + support framing
 Commence rendering, weather ideal - knauf Marmorit system

The scaffolding is being gradually dismantled now the roof is complete

Parking bays with dropped kerb

Perforated acoustic ceilings being installed

Louvred cupboard doors installed in the Laundry