Friday 14 March 2014

Science Block - Week 36 (week ending 16 March 2014)


The Science Block being prepared for render carrier boards

Fermacell wall boards line the laboratories 

Timber battening ahead of fixing the render carrier boards
Progress this week...

Activity/Observations

 Scaffold erection and dismantling is continuing as required, internal and external.
 Atrium acoustic ceiling is complete and decorated.
 Aluminium profile with concealed gutter is in progress to upper roof area and finishing of single ply roof membrane is being carried out as gutter is completed.
 Finishing to fermacell boards in 1st floor areas are continuing.
 Mechanical 1st fix continuing and 2nd fix has started.
 Electrical 1st fix containment is continuing.
 Acoustic flooring is complete to first floor classroom areas.
 Fitting of window boards are in progress.
 External battening is continuing and fitting of aqua panels are in progress.
 Air tests are complete to Soil and vent pipes and waste pipes branching off. All tested O.K.
 Testing of underground water main is in progress.