Monday 31 March 2014

Wyre Forest School - Week 38

Warmcell recycled insulation is pumped into the roof over the dining hall

Scaffolding prepared for the rection of the final wing to the primary age areas

Roof battening being fixed to phase secondary school areas

Changing rooms being erected around the hydrotherapy pool
Activity/Observations

 Timber frame erection is continuing to areas 1 and 2.
 Window and door fitting is in progress.
 Fitting of bitroc sheathing board is continuing external walls.
 Setting out of electrical boxes is in progress.
 Fitting of vertical slabs to the perimeter of the floor slab is progressing.
 Roof membrane and counter batten fixing has started to area 1.
 Blown insulation to roof cassettes has started.
 Scaffold erection to area 2 is continuing around perimeter of building.




So what's next?
 Continue scaffold erection, timber frame erection, fitting of bit roc, window fitting and battening, roof membranes and counter battening, vertical slabs to floor slab.