Monday 24 February 2014

Weekly Boarding Unit Week 33

We catch up on progress on the residential building for Wyre Forest School:

Activity/Observations
 Roof tiling, later stages
 Fermacell fire lining and plaster boarding continues to 1st and 2nd floors, includes taping/jointing. Also commence suspended acoustic resoilient bar ceiling support grids
 Electrical 1st fix cable installations includes containment, baskets, etc
 Sprinkler installations up to 1st Fix
 External cement panels now fixed, commence rendering - knauf Marmorit system
 Commence carpentry 1st fix, doors and linings to 1st floor circulation - fixed as site fire precaution only
 Mechanical 1st fix /plumbing + air ducting + boilers installed -
 CIS data systems stallations
 Cedar cladding, weather boarding + support framing
 Ground works - continue setts to channels, stone up car park and establish new bell mouth


Forming the new entrance on Moule Close

Heating and water pipes and electrical wiring above corridor ceilings

The garden laid out around the existing Scots Pine tree