Activity/Observations
Timber frame erection is continuing to areas 1 and 2. Roof decking has started to area 1.
Internal battening to concrete retaining wall is in progress.
Fitting of bitroc sheathing board is continuing external walls.
Setting out of electrical boxes is in progress.
Scaffold erection to area 2 is continuing around perimeter of building.
The first roof panels are lifted into place |
The first classroom wall with airtightness membrane and battened service zone. |
Floor and wall panels stacked and waiting to be lifted into place |