Friday 7 March 2014

Wyre Forest School - Contract week 34

Progress up to 2 March 2014:

Activity/Observations

 Cutting, placing and fixing of sole plates are complete.
 Timber frame erection is continuing to areas 1 and 2, additional crane being used..
 Service trench being excavated with water main and ducts being installed.


So what's next?
 Continue scaffold erection, fixing of sole plates, timber frame erection, service trenches and ducts.




Walls erected around the dining area, showing the servery hatch

Beams are fixed in place where the building turns a corner

Water, electric and data services are covered with an identity tape before the trench is backfilled