Friday 16 May 2014

Weekly Boarding Week 45 - week ending 18 May 2014

Activity/Observations
 Continue electrical 2nd fix
 Internal carpentry 2nd fix, architraves, skirting, boxing, fixed furniture, etc
 Mechanical 2nd fix /plumbing, etc
 Splash back tiling
 Carpet tiles to 1st floor study bedrooms
 Decorations, all areas where access allows also snagging/fine fill
 Ceilings lay-in tiles
 Ground workers, shape up, tarmac base, kerbs, channels, swales – progressing quickly

Garden area pathways

Garden area being laid out with curved rainwater channels

Carpet being laid in study bedroom

Shared living area - decoration and lighting almost complete