Continue electrical 2nd fix
Internal carpentry 2nd fix, architraves, skirting, boxing, fixed furniture, etc
Mechanical 2nd fix /plumbing, etc
Splash back tiling
Carpet tiles to 1st floor study bedrooms
Decorations, all areas where access allows also snagging/fine fill
Ceilings lay-in tiles
Ground workers, shape up, tarmac base, kerbs, channels, swales – progressing quickly
Garden area pathways |
Garden area being laid out with curved rainwater channels |
Carpet being laid in study bedroom |
Shared living area - decoration and lighting almost complete |