Tuesday 6 May 2014

Weekly Boarding - Week 43

Activity/Observations
 Continue electrical 2nd fix, lighting, outlets, etc
 Internal carpentry 2nd fix, architraves, skirting, etc, include 3rd and final stairway with support structure
 Mechanical 1st fix /plumbing wastes, etc
 Floor tiling to bathroom/showers rooms
 Decorations, all areas where access allows also snagging/fine fill
 Ceiling grids
 Ground workers, continue storm drains + slot drains and kerbs
 Coated weld mesh security fencing and timber rail fencing, include sprinkler tank

Acoustic ceiling being installed


The main kitchen being fitted out

bedroom corridor light fittings being installed

study bedroom with fitted desk area

En suite shower and basin