Tuesday 27 May 2014

Science Block Contract Week 46 (week ending 25 May 2014)

Activity/Observations

 Scaffold dismantling is continuing as required, internal and external.
 Finishing to fermacell wall boards are almost complete.
 Mechanical 2nd fix continuing.
 Electrical 2nd fix is continuing.
 2nd fix carpentry is continuing.
 Fitting of suspended ceiling grid is almost complete. Remainder of tiles to be fitted later.
 Fitting of aqua panels (render carrier boards) are continuing.
 External render and finishing coat is ongoing.
 Vinyl floor coverings are progressing well.
 Decorations to walls are continuing.
 Fitting of Lab furniture is continuing.
 M.F ceilings continuing.
 Timber staircase installation is complete.
 Balustrade to first floor circulation areas is fitted.
 Works to ramp and steps are progressing.
 Bris soleil, hoppers and down pipes fitted.


Brickwork for the edges of the access ramp

Sun shading to the south facing windows has been installed

Forming the external steps and ramp

First floor atrium area