Tuesday 27 May 2014

Weekly Boarding Unit - Week 46 - week ending 25 May 2014


The outdoor landscaped areas are taking shape

Kitchenette installation


Bathroom almost complete
 Activity/Observations
 Final stage electrical 2nd fix
 Final stage internal carpentry 2nd fix, architraves, skirting, boxing, fixed furniture, etc
 Mechanical 2nd fix /plumbing, commissioning
 Splash back tiling and edge trims
 Carpet tiles as access allows
 Decorations, all areas where access allows also snagging/fine fill
 Ceilings lay-in tiles
 Ground workers, shape up, tarmac base, kerbs, channels, swales
 Chlorination of water systems carried out Friday 23rd