Activity/Observations
Timber frame erection is continuing to areas 1 and 2.
Window and door fitting is continuing.
Fitting of bit roc board is continuing external walls.
Setting out of electrical boxes is in progress.
Fitting of vertical slabs to the perimeter of the floor slab is progressing.
Roof membrane and counter batten fixing has started to area 1.
Blown insulation to roof cassettes is in place to area 1.
Fitting of air tightness membranes are in progress.
Vapour barrier is being fitted to flat roof areas.
Scaffold erection to area 2 is continuing around perimeter of building.
So what's next?
Continue scaffold erection, timber frame erection, fitting of bit roc, window fitting and battening, roof membranes and counter battening, vertical slabs to floor slab, air tightness membranes.