Friday 11 April 2014

Habberley Learning Village - Weekly Boarding Week 40

Activity/Observations
 Fermacell fire lining and plaster boarding taping/jointing.
 Continue electrical 1st fix & 2nd fix
 Internal carpentry 2nd fix, doors (includes sliding doors + stud) and linings, stairs, kitchen units, cupboards, skirting, etc. Include doors to meter housing
 Mechanical 1st fix /plumbing
 Decorations/ painting
 Ceiling grids
 Water connection + chlorination
 Ground works storm drains to rear courtyard - water connection

The storm drains are laid... and encased in concrete

Doors are fitted and painting of walls and ceilings continues...

The old meter house has been refurbished as a garden store

Work continues on the rear garden

The water connection is made to the mains