Scaffold erection and dismantling is continuing as required, internal and external.
Single ply membrane to upper roof areas is fitted, outlets and edge trim to do.
Finishing to fermacell wall boards in 1st floor areas are continuing.
Mechanical 1st and 2nd fix continuing.
Electrical 1st and 2nd fix is continuing.
Acoustic flooring to 1st floor circulation areas is to complete.
Fitting of suspended ceiling grid is in progress to ground floor areas.
Acoustic / fire stopping has started to Classrooms.
Fixing of floor duct have started.
External battening is complete and fitting of aqua panels (render carrier boards) are continuing.
Render has started.
Fitting of cape cod boarding is continuing.
So what's next?
Scaffold erection, continue ducting, mechanical pipe work, 1st fix electrics, fermacell boarding to internal walls, single ply roof coverings, acoustic flooring, wall finishes externally, suspended ceilings.
Rendering of the block continues |
The upper level of the atrium |
Typical lab with services fed from below |
Ceiling being installed to conceal ductwork and cabling |