Monday 28 April 2014

Science Block : Week 42

The Science Block as seen from the Wyre forest School


Perimeter bench units being installed in the labs

Walls being decorated at the top of the atrium

Microlift being installed in the prep room. This will carry chemicals and lab equipment between the two floors.
Activity/Observations

 Scaffold erection and dismantling is continuing as required, internal and external.
 Finishing to fermacell wall boards in 1st floor areas are continuing.
 Mechanical 1st and 2nd fix continuing.
 Electrical 1st and 2nd fix is continuing.
 Fitting of suspended ceiling grid is in progress to ground floor and first floor areas and tiling started.
 Acoustic / fire stopping to Classrooms is continuing.
 External battening is complete and fitting of aqua panels (render carrier boards) are to complete.
 External render and finishing coat is progressing well.
 Fitting of cape cod boarding is continuing.
 Fitting of parapet capping started.
 Ground floor vinyl floor coverings are advanced.
 Ply covering being laid to 1st floor areas.
 Decorations to walls are continuing.
 Excavation and concreting of foundations for retaining wall has started.


So what's next?
 Scaffold dismantle, continue ducting, mechanical pipe work, 1st fix electrics, fermacell boarding to internal walls, single ply roof coverings, acoustic flooring, wall finishes externally, suspended ceilings, floor finishes.