Rendering of the facades continues |
Suspended ceilings being installed |
Toilet areas being constructed |
Timber cladding being installed |
Scaffold erection and dismantling is continuing as required, internal and external.
Single ply membrane to upper roof areas is fitted, outlets and edge trims almost complete.
Finishing to fermacell wall boards in 1st floor areas are continuing.
Mechanical 1st and 2nd fix continuing.
Electrical 1st and 2nd fix is continuing.
Acoustic flooring to 1st floor circulation areas is to complete.
Fitting of suspended ceiling grid is in progress to ground floor and first floor areas.
Acoustic / fire stopping to Classrooms is continuing.
External battening is complete and fitting of aqua panels (render carrier boards) are continuing.
Render is progressing well.
Fitting of cape cod boarding is continuing.
Liquid D.P.M. system has been applied to ground floor Classrooms and floor coverings have started.
Decorations to walls are in progress.
Lift installation has started.
So what's next?
Scaffold erection, continue ducting, mechanical pipe work, 1st fix electrics, fermacell boarding to internal walls, single ply roof coverings, acoustic flooring, wall finishes externally, suspended ceilings, floor finishes.