Thursday 24 April 2014

Weekly Boarding - week 41

Activity/Observations
 Continue electrical 2nd fix, lighting, outlets, etc
 Internal carpentry 2nd fix, doors (includes sliding doors + stud) and linings, stairs, kitchen units, cupboards, skirting, etc. Include doors to meter housing
 Mechanical 1st fix /plumbing wastes, etc
 Decorations, walls mostly to first floor
 Ceiling grids
 No ground works this week
 Site cabin removed and area cleared




Shared kitchen area being fitted

Landing at the top of the stairs

Doors and linings being fitted in the corridor