Continue electrical 2nd fix, lighting, outlets, etc
Internal carpentry 2nd fix, architraves, skirting, etc. Includes 3rd and final stairway
Mechanical 1st fix /plumbing wastes, etc
Floor tiling to bathrooms rooms
Decorations, walls mostly to first floor
Ceiling grids
Ground workers return, work to rear courtyard
Coated weld mesh security fencing, south of block
Work contnues on the garden areas around the building |
Pins placed to set out the garden paved areas |
Painting and decorating works continue, with the walls being finished in a soft 'clay white' |
Floor tiling works have commenced |