Weekly Boarding Unit - Progress Week 39

Progress this week..

 Fermacell fire lining and plaster boarding now advanced - includes taping/jointing.
 Continue electrical 1st fix & 2nd fix
 Internal carpentry 2nd fix, doors (includes sliding doors + stud) and linings, stairs, kitchen units, cupboards, skirting, etc.
 Mechanical 1st fix /plumbing
 Decorations
 Lift installations and commission
 Ground works continue

Photos from this week



The scaffolding has been removed. The blue and the yellow render panels denote the two 'houses' that the unit will be organised into.
 

View from the garden side.

The kitchen being installed


Ceilings have been installed in the corridor