Monday 9 June 2014

Wyre Forest School - week 48 (week ending 8 June 2014)


Timber frame being erected for the Foyer (temporary cross bracing)

The roof being placed over the hydrotherapy pool

Recycled newprint insulation is pumped via flexible pipes into the external walls


The walls around the staff room arebeing erected (view towards Foyer)

The west side of the building for Key Stage 3 and 4 students

Sprinkler pipework is fitted above the ciling in a classroom
Activity/Observations

 Timber frame erection is continuing.
 Window and door fitting is continuing as areas are complete.
 Fitting of bit roc board is continuing to external walls and blown cavity insulation started..
 Mechanical & Electrical works are in progress.
 Internal boarding to walls and ceilings are continuing.
 Acoustic separating floor system continuing (screed board floors to complete as areas become available).
 Fitting of vertical slabs to the perimeter of the floor slab is to be completed.
 Roof membrane and counter batten fixing is continuing.
 Roof tiling is continuing as areas become available.
 Single ply roof covering is in progress to flat roof areas.
 Fitting of air tightness membranes are continuing.
 Scaffold erection is continuing as required.
 Fitting of cedar fascias and barge boards are continuing as areas become complete.
 Cape cod cladding is in progress.
So what's next?
 Continue scaffold erection, timber frame erection, fitting of bitroc sheathing board, window fitting and battening, roof membranes and counter battening, vertical slabs to floor slab, air tightness membranes, roof coverings, internal wall boarding, acoustic floor.