The Science Block with the scaffolding removed |
The south elevation nearing completion |
The foyer area |
Light fittings have been added to the atrium at first floor |
Scaffold dismantling is continuing.
Finishing to fermacell wall boards are almost complete.
Mechanical 2nd fix continuing.
Electrical 2nd fix is continuing.
2nd fix carpentry is continuing.
Fitting of suspended ceiling grid is almost complete. Fitting of tiles in progress.
External render and finishing coat is ongoing.
Vinyl floor coverings are progressing well and carpet tiles started.
Decorations are continuing.
Fitting of Lab furniture is continuing.
Metal framed suspended ceilings continuing.
Works to ramp and steps are progressing.
So what's next?
Scaffold dismantle, 2nd fix M & E, internal decorations, wall finishes externally, suspended ceilings, floor finishes, furniture fitting, 2nd fix Carpentry, external works.