Monday 16 June 2014

Habberley Learning Village – Early Years Hub - Build week 4

Activity/Observations
 Reduce level dig, over-site working to south of building
 Set out building footprint, reduced level dig + cart away
 Stone blind below building – now in-part ready for formwork
 Commence drainage to north of building

Two areas of extra dig due to excessive root contamination and soft sand at formation – extra dig at 600mm also over dig to step again due to excessive root contamination
 Excavated material clean sand, mostly firm to formation

Drainage trenches excavated

Clay drainage pipes laid under the building

hardcore fill to go under the raft foundation