The brick shed has been demolished to make way for the Campus Square |
The excavation for the Early Years Hub is progressing well |
The brick walls being demolished |
Reduce level dig, over-site
Set out building footprint, reduced level dig + cart away
Stone below building – now in-part ready for formwork
Services cat scanned and locations ascertained, adjacent retaining wall south of building
Commence/complete demolition of existing 3 bay brick built store building
Excavated material clean sand, firm to formation