Habberley Learning Village - Science Block - Week 49

Activity/Observations

 Mechanical 2nd fix continuing.
 Electrical 2nd fix is continuing.
 2nd fix carpentry is continuing.
 Fitting of suspended ceiling grid is almost complete. Fitting of tiles in progress.
 External render and finishing coat is ongoing.
 Floor coverings are almost complete.
 Decorations are continuing.
 Fitting of Lab furniture is continuing.
 Metal framed ceilings continuing.
 Works to ramp and steps are progressing.


So what's next?
 2nd fix M & E, internal decorations, wall finishes externally, suspended ceilings, floor finishes, furniture fitting, 2nd fix Carpentry, external works.




Atrium first floor with shared teaching space and teaching focus wall

Lab with wall benching and demonstration bench installed

Work to prepare the science garden


Brickwork walls forming the entrance ramp