Final stage electrical 2nd fix, testing
Final stage internal carpentry to completion
Final stage Mechanical 2nd fix /plumbing, commissioning
Carpet tiles mostly complete to first floor. Carpet and rubber tac-tile flooring to ground floor
Final stage painting/decoration + Mural
Final stage ceilings lay-in tiles in-conjunction with services
Ground workers, shape up, tarmac base, kerbs, channels, swales, gullies, etc
Fencers return
Landscaping
Comments
Externals snagged Monday internals, Friday
Within the enclosed garden, individual garden spaces are defined by low fences |
The main kitchen is almost complete |
Flat-packed furniture is being assembled |