Friday 29 November 2013

Weekly Boarding Unit: Contract Week 21

First floor walls awaiting roof cassette

The same view with roof cassette and roof counterbattens on forming the roof overhangs


Acoustic insulation is added to the ground floor ceilings
 What has been happening on site this week?

Continue erection of timber frame, now at roof level - roof cassettes now at around 50% complete – roofing counter battens (70mm x 75mm)
 Continue second skin sheathing and timber framing - this will form a thermal 'wrap' around the building.
 Plinth Damp proof membrane– overlay plinth DPM – install 150mm insulation + slab on edge to form a 300mm high plinth around the building. – now advanced
 Internal partition walls and floor zone 1st floor acoustic insulation + netting.
 Commence door and window installations
 1st fix plumber soil and vent pipes
 Air tightness membrane + taping, on-going