Monday 25 November 2013

Wyre Forest School: Week 20




Starting to build the landscape retaining wall to the Primary play area. It will be finished in buff coloured brickwork.
 


What has been happening on site this week

Activity/Observations

 Block work to lift shafts continuing and scaffold erection as required.
 Insulation, drainage and backfill to rear of retaining wall is complete.
 Make up levels in recycled hardcore is almost complete to main car park area, curb laying, ducting and drainage in progress.
 Back wash tank to hydro pool is being fitted.
 Shutters and steelwork have started to south east brickwork retaining wall. This forms the edge of the primary age playground.
So what's next?
 Continue drainage, south east retaining wall, floor slab / cantilevered floor around hydro pool, kerbs to car park.
Behind the scenes, New World Timber Ltd are preparing for the first section of timber walls and roof in their factory.

This attenuation tank will take waste water from the hydrotherapy pool and discharge it slowly to the sewer




The car park at the school being formed, kerbs being put into place.
 