Monday 18 November 2013

Wyre Forest School: Week 19



The concrete shell of the hydrotherapy pool seen from above
 What's been happening on site this week?

 Block work to lift shafts continuing and scaffold erection continuing as required.
 Insulation, drainage and backfill to rear of retaining wall almost complete.
 Make up pf levels in recycled hardcore is continuing to main car park area.

Sports pitch area Laying of hardcore and concrete edgings to Sports pitch path has started.

So what's next? Continue drainage, floor slab / cantilevered floor around hydrotherapy pool, shaping of terrace area, backfill to retaining wall, sport pitch paths.




Scaffolding being put up around the lift shafts. The lift shafts are being built in concrete blockwork.