Second skin webbed beams being fixed in position


What's been happening on site this week?

Activity/Observations
 Continue erection of timber frame, partitions/structure now 80% complete overall, including position and fix floor cassettes
 Temporary bracing ongoing
 Commence second skin sheathing and timber framing - this will be insulated a forms a 'wrapping' layer around all structural elements to avoid cold spots in the structure and improve overall insulation to very high standards
 Air tight membrane
 Position glu-lam first floor support beams + steels
 Continue scaffold adjustments with 3rd lift and loading bays
 Continue gabion assembly, make up levels to sprinkler tank base area and grade to rear
Comments
 Outer sheathing/framing progressing well in-conjunction with timber frame erection
Programme*
So what's next? 2 further weeks of timber frame erection
 Continue second skin sheathing and non structural elements


First floor walls being craned into place