Friday 22 November 2013

Weekly Boarding Unit: Week 20

The tops of the internal walls at roof level awaiting the roof cassettes

What's been happening on site this week? Continue erection of timber frame, now at roof level - commence roof cassettes
 Temporary bracing ongoing
 Continue second skin sheathing and timber framing
 Plinth: install 150mm insulation and slab on edge to form a plinth to the timber cladding.
 Air tight membrane and taping to ensure airtightness, reduce draughts and heat loss
 Continue scaffold adjustments
So what's next? Commence window and doorway installations



View from the garden side of the Weekly Boarding Unit