Activity/Observation
 M & E works are continuing.
 Finishes to wall boarding and ceilings are continuing.
 Acoustic separating floor system repairs and replacing of areas to complete.
 Fitting of vertical slabs to the perimeter of the floor slab is almost complete.
 Single ply roof covering and flashings almost complete.
 Fitting of cedar fascia's, barge boards and window cheeks are almost complete.
 Decorations are continuing.
 Metal framed bulkheads, ceilings and suspended ceiling grids being erected.
 Wall tiling is continuing, including tiling to hydro pool.
 Sanitary items being fitted.
 Plumbing panels are continuing, basin and hinged rail fixings to address.
 Works within Atrium is progressing.
 Gutter fixing is to complete.
 2nd fix Carpentry is continuing.
 Storm water drainage connections from down pipe positions continuing.
 Face brickwork to retaining walls are progressing.
 Laying of vinyl floor covering is progressing to various areas, including laying of liquid D.P.M.
 Furniture fitting is continuing.
 General external works continuing.
 Lift installation to both areas are continuing.
Dining Hall with ceiling tiles installed

Catering kitchen units being installed

Floor tiles are laid in the hydrotherapy pool hall

Bathroom Management Area

Floor being prepared in the Atrium

Progress on the outdoor areas