Monday 22 December 2014

Habberley Learning Village, Early Years Hub - Week 31

Activity/Observations
 Internal MF partitions + boarding + skim now advanced
 Floor vinyl, to rooms requiring fixed furniture follow on
 Install kitchenette units + fixed furniture
 Electrical 2nd fix
 Mechanical 2nd fix, fan coil heaters, etc.
 Plumber 1st fix
 Mist coat and 1st coat painting
 Ceiling grids + lighting
 Carpentry 2nd fix – doors, linings, skirting, architraves,
 IPS, vanity units and proprietary cubicle partitions
 CIS data cabling
 Slab on edge external plinth
 Paving, steps ramps, etc. west of building/campus square - Further drainage around the building
 Mono blocks, campus square around 60% complete
 Shutter and pour concrete bases to canopy, throughout route

The foundations for the covered route to the Early Years Hub as it approaches St. John's Primary

Outside areas beside the EYH

Progress on the classroom areas