Finishes to wall boarding and ceilings are continuing.
Acoustic separating floor system to complete.
Fitting of vertical slabs to the perimeter of the floor slab is almost complete.
Single ply roof covering and flashings almost complete.
Fitting of cedar fascia's, barge boards and window cheeks are almost complete.
Decorations are continuing.
M.F. bulkheads, ceilings and suspended ceiling grids being erected.
Wall tiling is continuing, including tiling to hydro pool.
Soil and vent and sink waste pipes being fitted.
Plumbing panels are continuing.
Works within Atrium is progressing.
Gutter fixing is to complete.
2nd fix Carpentry is continuing.
Storm water drainage connections from down pipe positions continuing.
Face brickwork to retaining walls are progressing.
Laying of vinyl floor covering is progressing to various areas, including laying of liquid D.P.M.
Sports hall floor is in progress.
Furniture fitting is continuing.
General external works started.
Lift installation to both areas are continuing.
Fitting of climbing frames almost complete.
So what's next?
Continue external works, roof covering flashings, internal wall boarding,decorations and acoustic floor, 2nd fix Carpentry, M & E works, wall tiling, ceilings, floor covering.
Progress on a Key Stage 4 first floor classroom |
Lighting being installed in the assembly hall |
Primary classbase |
Sports Hall with basketball nets installed |
Units installed in the food tech room |
Hydrotherapy pool with wall and floor tiling |
School office with view of main entrance |
Progress on the outdoor areas to the west of the school |
Retaining wall to Primary hard play |
Foyer |