Monday 8 December 2014

Early Years Hub - Week 29

View from Campus Square

Open plan nursery area

Reception class area

The curved entrance lobby

The main entrance
Activity/Observations
 Internal Metal framed partitions + boarding + skim now advanced
 Floor vinyl, commencing west of building
 Install kitchenette units
 Electrical 2nd fix
 Mechanical 2nd fix, fan coil heaters, etc.
 Plumber 1st fix
 Mist coat and 1st coat painting
 Ceiling grids
 Carpentry 2nd fix - linings, skirting, architraves
 Toilet plumbing, vanity units and proprietary cubicle partitions
 Data networks
 Cedar soffits
 Slab on edge external plinth
 Paving, steps ramps, etc. west of building/campus square - Further drainage around the building
 Tarmac, upper campus square
 Reduce levels to canopy, commencing adjacent existing school