Monday 1 December 2014

Early Years Hub - Week 28

Activity/Observations
 Internal Metal framed partitions + boarding + skim
 Floor vinyl, commencing west of building
 Install kitchenette units
 Electrical 2nd fix
 Mechanical 2nd fix, fan coil heaters, etc.
 Plumber 1st fix
 Mist coat painting
 Ceiling grids
 Carpentry 2nd fix – linings, skirting, architraves
 IPS, vanity units and proprietary cubicle partitions
 CIS
 Cedar soffits
 Retainer block walls, paving, steps ramps, etc. west of building/campus square - Further drainage around the building
 Prep ahead of insulation and slab on edge external plinth