M & E works are continuing.
Finishes to wall boarding and ceilings are continuing.
Fitting of vertical slabs to the perimeter of the floor slab is almost complete.
Single ply roof covering and flashings almost complete.
Fitting of cedar fascias, barge boards and window cheeks are almost complete.
Decorations are continuing.
Tiles to ceiling being fitted.
Wall tiling is continuing, including tiling to hydro pool.
Sanitary items being fitted.
Plumbing panels are continuing, basin and hinged rail fixings to address.
Gutter fixing is to complete.
2nd fix Carpentry is continuing.
Storm water drainage connections from down pipe positions continuing.
Face brickwork to retaining walls are almost complete.
Laying of vinyl floor covering is progressing to various areas, including laying of liquid D.P.M.
Furniture fitting is to complete.
General external works continuing.
Lift installation to both areas are almost complete.
Work on the eastern (primary) outdoor areas |
Outside the main entrance - preparing for the base for the canopy |
Western outdoor areas - secondary games courts |
Hoist track over the hydrotherapy pool |
Progress on the main foyer |
Stair 3 and lift up to Campus Square |
Key Stage 4 Classroom with glazed group room |